BICSI RCDD RCDDv14.1 Question # 31 Topic 4 Discussion

RCDDv14.1 Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?


A.

Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance


B.

Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction


C.

Work with program sponsor to compile impact analysis data to obtain additional funding for the program


D.

Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction