BICSI RCDD RCDDv14.1 Question # 67 Topic 7 Discussion

RCDDv14.1 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.

What is a critical component of the Program Schedule Management Process?


A.

A list of all the projects that team members are working on


B.

Activity or component start and finish dates, as well as intermediate milestones


C.

Time management training programs for all team members, as well as the project managers


D.

Skill levels of the various project team members, as well as the project managers