Question #: 84
Topic #: 9

A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha's program closure plan?


A.

Execute the transition plan and Include Knowledge transfer to transition Alpha support to operations


B.

Keep the Alpha program open until support is no longer required, then execute program closure


C.

Adjust Alpha's exit criteria to ensure its support is included in the Beta program


D.

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta