CIMA Operational P1 Question # 52 Topic 6 Discussion

P1 Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

A project has an expected value of $165,250.

The estimates of cash inflows and their probabilities are:

P1 Question 52

What is the missing cash inflow?

Give your answer as a whole number.