CIMA Operational P1 Question # 72 Topic 8 Discussion

P1 Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

A company is choosing between three projects, Project P, Project Q and Project R using minimax regret as the criterion for the decision. The outcome from each project is dependent on future economic growth. If this is strong, returns will be P $5,000, Q $6,500 and R $7,200. If it is weak, returns will be P $3,500, Q $4,800 and R $4,200.

Place the correct figures into the table to show the maximum regret for each project.

P1 Question 72