Forecast sales demand of product W next period is 6,800 units. Product W requires 5 kg of material Y, seven hours of skilled labour and six hours of semi-skilled labour.

Availability of resources for next period is forecast as follows:

P1 Question 76

No inventories are held.

What is the principal budget factor for next period?


A.

Sales demand


B.

Availability of material Y


C.

Availability of skilled labour


D.

Availability of semi-skilled labour