ECCouncil CCISO 712-50 Question # 120 Topic 13 Discussion

712-50 Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD. This is an example of


A.

Risk Tolerance


B.

Qualitative risk analysis


C.

Risk Appetite


D.

Quantitative risk analysis