A platform engineer is at a customer site to replace a failed Dell EMC PowerScale Gen 6 node. After removing the compute module, they observe lit LEDs inside the removed node.

What is the recommended response?


A.

This is not normal; they need to shut down the partner node.


B.

There is an internal electrical fault; they should call support.


C.

The node is not yet completely shut down; they should wait.


D.

This is normal; they should continue with the procedure.