ISC 2 Credentials CISSP Question # 46 Topic 6 Discussion

CISSP Exam Topic 6 Question 46 Discussion:
Question #: 46
Topic #: 6

Which of the following is TRUE about Disaster Recovery Plan (DRP) testing?


A.

Operational networks are usually shut down during testing.


B.

Testing should continue even if components of the test fail.


C.

The company is fully prepared for a disaster if all tests pass.


D.

Testing should not be done until the entire disaster plan can be tested.