Exam CTFL_Syll_4.0 All Questions
Exam CTFL_Syll_4.0 All Questions

View all questions & answers for the CTFL_Syll_4.0 exam

iSQI ISTQB Foundation Level CTFL_Syll_4.0 Question # 1 Topic 1 Discussion

CTFL_Syll_4.0 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Which of the following statements about estimation of the test effort is WRONG?


A.

Once the test effort is estimated, resources can be identified and a schedule can be drawn up.


B.

Effort estimate can be inaccurate because the quality of the product under tests is not known.


C.

Effort estimate depends on the budget of the project.


D.

Experience based estimation is one of the estimation techniques.