Consider the following examples of risks identified in different software development projects:

[I]. It may not be possible to generate the expected workloads to run performance tests, due to the poor hardware equipment of the machines (load injectors) that should generate these workloads

[II]. A user’s session on a web application is not invalidated after a certain period of inactivity (configured by the system administrator) of the user

[III]. The test team will not have an adequate requirements specification (since many requirements will still be missing) by the time test design and analysis activities should begin according to the test plan

[IV]. Following a failure, the system is unable to continue to maintain its pre-failure operation and some data becomes corrupted

Which of the following statements is true?


A.

[II] and [IV] are product risks: [I] and [III] are project risks


B.

[II] and [III] are product risks, [I] and [IV] are project risks


C.

[I], and [IV] are product risks: [II] and [III] are project risks


D.

[I], [II] and [III] are product risks; [IV] is a project risk