iSQI ISTQB Foundation Level CTFL_Syll_4.0 Question # 45 Topic 5 Discussion

CTFL_Syll_4.0 Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

A company runs a pilot project for evaluation of a test automation tool. Which of the following is NOT a valid object of this pilot project?


A.

Get familiar with the functionality and options of the tool


B.

Check haw the tool fits to the existing test processes


C.

Train all testers on using the tool


D.

Decide upon standards for tool implementation