InAgile projects, theTest Analyst’s involvementtypically startsat the beginning of the project.
Test Analysts workcollaboratively with developers, product owners, and other team membersfrom the outset to ensure thattesting is integrated into the development process.
Option A (Beginning of the first iteration)is too late since planning and discussing test approaches begin earlier.
Option B (After signing off user stories)contradicts the Agile principle of continuous involvement.
Option C (In parallel with coding)also occurs too late since testing considerations should start during planning.
The correct answer isD (At the beginning of the project).