Question #: 5
Topic #: 1

When would the Test Analyst’s involvement in an Agile project normally start?

SELECT ONE OPTION


A.

At the beginning of the first iteration


B.

As soon as the user stories have been signed-off


C.

In parallel with coding for the first iteration


D.

At the beginning of the project