Microsoft Certified: Windows Server Hybrid Administrator Associate AZ-801 Question # 13 Topic 2 Discussion

AZ-801 Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

You have a server that runs Windows Server.

You plan to back up the server to an Azure Recovery Services vault once per week starting on the next Saturday.

You need to schedule the weekly backup and perform the initial backup as soon as possible.

In which order should you perform the actions? To answer, move all actions from the list of actions to the answer are and arrange them in the correct order.

AZ-801 Question 13