Comprehensive and Detailed Explanation From Exact Extract:
The stakeholder engagement and communications plan outlines the identification, analysis, prioritization, and engagement strategy for stakeholders. It emphasizes two-way communication.
MSP Foundation, 5th Edition defines it as:
“A plan that describes how stakeholders are identified, prioritized, and engaged over the life of the programme, and how two-way communication will be maintained.”
Hence, D is the correct answer.
—