Comprehensive and Detailed Explanation From Exact Extract:
ThePlan progressive deliveryprocess defines the tranche-based execution of the programme, covering staffing, procurement, and chunked delivery pacing. From Good‑e‑Learning:
The process defines acquisition and resource management approaches (Objective 3)
It also ensures the operational areas can support the speed of delivery (Objective 4)
Objectives 1 and 2 (benefits in BAU and risk registers) are part of Embed or Evaluate, not directly Plan Progressive Delivery. Hence, the correct answer isC (3 and 4).