Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses. They've asked you to determine the cost variance for the program. What is the cost variance based on this information?


A.

-$27,500 B. -$77,500 C. -$61,111 D. .90