PMI PgMP Question # 104 Topic 11 Discussion

PgMP Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.

What should the program manager do next?


A.

Reassess the project manager’s credentials


B.

Assign a different project manager


C.

Review the skill requirements of the project


D.

Apply the competence assessment techniques to resolve the issue