Question #: 108
Topic #: 11

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?


A.

Institute an incentive program to create competition among the team members.


B.

Make the project manager share an office with a more assertive team member.


C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.


D.

Create an online message board so team members can see and respond to everyone’s ideas.