PMI PgMP Question # 110 Topic 12 Discussion

PgMP Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program.

The benefits register should include which of the following?


A.

List of planned benefits, earned value (EV), and responsible person


B.

List of planned benefits, measurement method, and component mapping


C.

List of planned benefits, benefit creator, and realization date


D.

List of planned benefits, stakeholders, and risk level