PMI PgMP Question # 111 Topic 12 Discussion

PgMP Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?


A.

Work breakdown structure


B.

Program network diagram


C.

Program scope baseline


D.

Activity list