PMI PgMP Question # 118 Topic 12 Discussion

PgMP Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?


A.

Finish on constraints


B.

Discretionary dependencies


C.

Mandatory dependencies


D.

Benefits management dependencies