PMI PgMP Question # 124 Topic 13 Discussion

PgMP Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?


A.

Crash the program


B.

Add lead time to the program


C.

Trim the program scope


D.

Fast track the program