Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PgMP All Questions
Exam PgMP All Questions

View all questions & answers for the PgMP exam

PMI PgMP Question # 27 Topic 3 Discussion

PgMP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?


A.

Program governance


B.

Program risk management


C.

Quality assurance


D.

Issue owner management


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.