PMI PgMP Question # 38 Topic 4 Discussion

PgMP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?


A.

Program scope statement definition


B.

Feasibility study creation


C.

Business case creation


D.

Program charter creation