Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PgMP All Questions
Exam PgMP All Questions

View all questions & answers for the PgMP exam

PMI PgMP Question # 41 Topic 5 Discussion

PgMP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A program manager recognizes that a successful resource being used in project A could also be used in project B.

What should the program manager do first to leverage the utilization of this resource?


A.

Assign project A's resource to project B.


B.

Reassign the resource to project B after project A ends.


C.

Prioritize the resource to optimize their use across both projects A and B.


D.

Mitigate risk by leveraging other resources in project A.


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.