Question #: 53
Topic #: 6

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change

request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?


A.

The program governance board


B.

The program customer


C.

The program management office (PMO)


D.

The project governance board