Question #: 61
Topic #: 7

You are the program manager for the HNY Corporation and you complete programs for other companies in your role. You have just been assigned a new program that is very similar to a recently completed program you did for your company. Management has asked you to create a cost estimate for the program so you base your current cost estimate on the recently finished program. What type of estimating technique have you used in this instance?


A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Rough order of magnitude