PMI PgMP Question # 74 Topic 8 Discussion

PgMP Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template, while others prefer another.

How should the program manager decide which template is appropriate?


A.

Review the issue with the program management office (PMO) to determine which template to use.


B.

Review the issue with the project managers and come to mutual agreement on which template to use.


C.

Meet with the program governance board to select an appropriate template.


D.

Allow the component project managers to use their preferred templates.