PMI-001 Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

What is the critical chain method?


A.

A technique to calculate the theoretical early start and finish dates and late start and finish dates


B.

A schedule network analysis technique that modifies the project schedule to account for limited resources


C.

A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost


D.

A technique to estimate project duration when there is a limited amount of detailed information about the project