PMI Project-Management-Professional PMI-001 Question # 100 Topic 11 Discussion

PMI-001 Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

Which of the following buffers protects the target finish date from slippage along the critical chain?


A.

Critical buffer


B.

Project buffer


C.

Duration buffer


D.

Feeding buffer