Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMI-001 All Questions
Exam PMI-001 All Questions

View all questions & answers for the PMI-001 exam

PMI Project-Management-Professional PMI-001 Question # 88 Topic 11 Discussion

PMI-001 Exam Topic 11 Question 88 Discussion:
Question #: 88
Topic #: 11

The following is a network diagram for a project.

PMI-001 Question 88

The free float for Activity H is how many days?


A.

4


B.

5


C.

10


D.

11


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.