Question #: 109
Topic #: 13

Which tools or techniques are used in the Plan Schedule Management process?


A.

Benchmarking, expert judgment, and analytical techniques


B.

Statistical sampling, benchmarking, and meetings


C.

Negotiations, pre-assignment, and multi-criteria decision analysis


D.

Expert judgment, analytical techniques, and meetings


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer: