PMI Project-Management-Professional PMI-001 Question # 131 Topic 15 Discussion

PMI-001 Exam Topic 15 Question 131 Discussion:
Question #: 131
Topic #: 15

In a project, total float measures the:


A.

Ability to shuffle schedule activities to lessen the duration of the project.


B.

Amount of time an activity can be extended or delayed without altering the project finish date.


C.

Cost expended to restore order to the project schedule after crashing the schedule.


D.

Estimate of the total resources needed for the project after performing a forward pass.