PMI Project-Management-Professional PMI-001 Question # 141 Topic 16 Discussion

PMI-001 Exam Topic 16 Question 141 Discussion:
Question #: 141
Topic #: 16

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?


A.

Negative


B.

Zero


C.

Positive


D.

Free