PMI Project-Management-Professional PMI-001 Question # 144 Topic 16 Discussion

PMI-001 Exam Topic 16 Question 144 Discussion:
Question #: 144
Topic #: 16

The Closing Process Group includes which of the following Knowledge Areas?


A.

Project Risk Management and Project Procurement Management


B.

Project Integration Management and Project Procurement Management


C.

Project Risk Management and Project Integration Management


D.

Project Integration Management and Project Quality Management