PMI Project-Management-Professional PMI-001 Question # 160 Topic 18 Discussion

PMI-001 Exam Topic 18 Question 160 Discussion:
Question #: 160
Topic #: 18

Completion of the product scope is measured against the product:


A.

prototypes


B.

requirements


C.

analyses


D.

benchmarks