Question #: 163
Topic #: 18

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?


A.

Finish-to-start planning


B.

Rolling wave planning


C.

Short term planning


D.

Dependency determination