PMI Project-Management-Professional PMI-001 Question # 14 Topic 2 Discussion

PMI-001 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

The Perform Integrated Change Control process occurs in which Process Group?


A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning