PMI Project-Management-Professional PMI-001 Question # 194 Topic 21 Discussion

PMI-001 Exam Topic 21 Question 194 Discussion:
Question #: 194
Topic #: 21

The scope management plan and scope baseline are contained in:


A.

organizational process assets


B.

a requirements traceability matrix


C.

the project charter


D.

the project management plan