PMI Project-Management-Professional PMI-001 Question # 38 Topic 4 Discussion

PMI-001 Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

Using the following data, what is the Schedule Performance Index (SPI)?

EV= $500 PV= $750 AC= $1000 BAC= $1200


A.

0.67


B.

1.5


C.

0.75


D.

0.5