PMI Project-Management-Professional PMI-001 Question # 29 Topic 6 Discussion

PMI-001 Exam Topic 6 Question 29 Discussion:
Question #: 29
Topic #: 6

The total of the planned value (PV) is also known as:


A.

work breakdown structure (WBS).


B.

schedule target.


C.

performance measurement baseline (PMB).


D.

earned value baseline.