PMI Project-Management-Professional PMI-001 Question # 33 Topic 7 Discussion

PMI-001 Exam Topic 7 Question 33 Discussion:
Question #: 33
Topic #: 7

Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?


A.

Analogous Estimating


B.

Expert Judgment


C.

Optimistic Estimates


D.

Reserve Analysis