PMI Project-Management-Professional PMI-001 Question # 37 Topic 7 Discussion

PMI-001 Exam Topic 7 Question 37 Discussion:
Question #: 37
Topic #: 7

During which process does the project team receive bids and proposals?


A.

Conduct Procurements


B.

Plan Procurements


C.

Estimate Costs


D.

Control Budget