PMI Project-Management-Professional PMI-001 Question # 43 Topic 7 Discussion

PMI-001 Exam Topic 7 Question 43 Discussion:
Question #: 43
Topic #: 7

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?


A.

Perform Quality Assurance


B.

Direct and Manage Project Work


C.

Monitor and Control Project Work


D.

Perform Integrated Change Control