The three types of estimates that PERT uses to define an approximate range for an activity’s cost are:


A.

Parametric, most likely, and analogous.


B.

Least likely, analogous, and realistic.


C.

Parametric, optimistic, and pessimistic.


D.

Most likely, optimistic, and pessimistic.