PMI Project-Management-Professional PMI-001 Question # 59 Topic 9 Discussion

PMI-001 Exam Topic 9 Question 59 Discussion:
Question #: 59
Topic #: 9

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?


A.

Critical path method


B.

Critical chain method


C.

Resource leveling


D.

Schedule network analysis