PMI Agile PMI-ACP Question # 98 Topic 10 Discussion

PMI-ACP Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?


A.

Lead time, throughput, and due date performance


B.

Work in progress limits, Kanban board, and time boxes


C.

Work item types, sprint cadences, and defect classes


D.

Burndown charts, scatter diagrams, and throughput