Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMI-ACP All Questions
Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

PMI Agile PMI-ACP Question # 119 Topic 12 Discussion

PMI-ACP Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

What should a team do when they complete all sprint goals earlier than expected?


A.

Begin working on an item in the backlog


B.

Ask the Scrum Master to select an item from the backlog on which to work


C.

Ask the Product Owner to select an item from the backlog on which to work


D.

Jointly decide with the Scrum Master on an item from the backlog on which to work


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.