PMI Agile PMI-ACP Question # 137 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 137 Discussion:
Question #: 137
Topic #: 14

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?


A.

Project velocity should be stable overtime.


B.

Moving velocity from 27 to 35 is a decrease in productivity.


C.

A burndown chart compares planned versus actual, not velocity.


D.

Velocity is iterative and will only be used for sprint numbers.